Roofing work
Roofing work: Execution periods: - Pitched roofs: Feb. 15 - May 13, 2027 - Flat roofs: Apr. 20 - May 28, 2027 Demolition - Flat roofs (150sqm+315sqm) Removal and disposal of lightning protection, cladding, insulation and bitumen waterproofing - Pitched roofs (925sqm+925sqm) Removal and disposal of lightning protection, hatches, drainage, dormer cladding, roofing Carpentry and woodwork - Additional purlins (4 pcs.) - Rafter reinforcement Roof waterproofing (150sqm + 315sqm) - Roof waterproofing - Fall protection - Parapet construction - Drainage - Insulation Roofing work (925 sqm + 925qm) - Roofing - Roof windows - Ins...