Modernisation of Hagen Central Station VST - Lot 01.3 - New construction of platforms 1 & 5, expansion of pedestrian underpass
The subject of the tender is the construction work for the modernisation of Hagen Central Station within the framework of the project "Lot 01.3 – New construction of platforms 1 and 5 and expansion of the pedestrian underpass". The scope of services essentially includes site installation and site logistics under railway operations, the dismantling of existing platform, roof, stair, elevator and tunnel facilities including disposal of the resulting materials, earthworks, civil engineering and drainage work, cable civil engineering work, the new construction of platform edges and platform areas, the construction of platform roofs as well as
Translated automatically from the original language, so check the official notice for the exact wording. Original title: Modernisierung VST Hagen Hbf - VP 01.3 - Neubau Bahnsteige 1&5, Ausbau PU