New construction and renovation of primary and secondary school Laufen - courtyard with pipe construction
Construction measure: new construction and renovation of primary and secondary school Laufen, conversion of courtyard with pipe construction. Construction site: Kohlhaasstraße 4, 83410 Laufen. Planned execution period: 12.03.2027 to 14.05.2027. As part of the above construction measure, before demolition of the existing gymnasium building, the central courtyard area of the primary school must be created. The scope of services initially includes the removal of existing asphalt and concrete stone paving areas including edging as well as the building‑side eave strip with gravel bedding. The existing terrain with a height difference of approx. 1.50 m is ent
Translated automatically from the original language, so check the official notice for the exact wording. Original title: Neubau u. Sanierung Grund- u. Mittelschule Laufen - Pausenhof mit Leitungsbau