The contracting authority intends to build a non-public charging infrastructure at the depot of Regiobus Uhlendorff GmbH & Co. KG, Neustadtstraße 38, 34399 Wesertal. The following execution deadlines are agreed as binding deadlines (contract deadlines) for the completion of the services from lots 1, 2 and 3: Lot 1: Installation of transfer station / MV commissioning: 15/08/2027 Lot 2: Installation and commissioning (including trial operation of 5 working days: 15/08/2027 Lot 3: Completion 30/04/2027 There is the possibility of a site visit. The contracting authority recommends e